Burwood–Mairehau · 10 November 2026 · Follow-up

Still going the long way round.

Back in September, I wrote about the roadworks around Burwood and Mairehau. Now it’s November, and the diversions are still in place. The pipe work is meant to finish in early December, and the traffic lights aren’t due to get started until late next year. That’s a lot of waiting for one neighbourhood.

Illustration: An unlit traffic light at a wet suburban intersection at night, with an orange DETOUR sign and two road cones reflected in a puddle
Illustration
The dates that matter

The extra pipe repairs were due to run into early November. The rest of the wastewater work is due to finish in early December. Then there’s the intersection upgrade, scheduled to start in late 2027.

The September story, with the longer timeline and road map →

How it stretches out

And then there’s the next lot.

Burwood–Mairehau programme as at 10 November 2026 Route 7 notice spans 9 June to the 10 November reference date, with no end date given. Council planned additional repairs from 7 September to early November and remaining work from early November to early December. Amber bars show planned dates. A separate intersection stage is scheduled to start in late 2027, duration unknown. The published programme · 10 November 2026 The bus diversion notice and Council’s planned work dates Jun 2026 Jul Aug Sep Oct Nov Dec Route 7 westbound notice No announced end date 9 June → notice still listed on 10 November Additional pipe repairs Council’s planned window 7 September → early November (target) Remaining wastewater work Council’s planned window Early November → early December (target) 10 Nov NEXT STAGE · LATE 2027 Traffic-light work is due to start. The October Board report gives no finish date. Teal: listed notice period Dashed amber: planned work Vertical line: 10 November “Early” dates are approximate. Council and Metro links are in the story. · Ed Groenendaal
The blue bar runs from the start of Metro’s diversion notice to 10 November. The amber bars show Council’s planned work dates; “early” November and December are approximate. These are different stages, with different restrictions along the way. Sources: Council, Metro and the October Board report.

November, and we’re still on diversion

The diversions are still in place today, 10 November. For those of us living here, the disruption is very much part of everyday life.

Council says the dig at Burwood Road and Mairehau Road turned up another section of damaged wastewater pipe. It says the damage wasn’t visible before excavation, so there was more to repair than expected. Fair enough—sometimes you don’t know what’s underneath until you open it up. [1]

The timetable put those extra repairs between 7 September and early November, with Mairehau Road reopening once that section was finished. The remaining wastewater work was then due to run from early November to early December. Council says the two parts couldn’t be done at the same time. [1]

Meanwhile, Metro’s Route 7 page still carries the westbound diversion that began on 9 June, with the familiar “until further notice”. Putake Drive, Rothesay Road, back down Burwood Road, into the hospital and out again. Five months on, that notice is still there. [2]

We’re now at the point when the extra repairs were supposed to be wrapping up, yet we’re still taking the diversions. The early-November target hasn’t brought an end to the disruption.

The traffic lights will have to wait until late next year

The delay I mentioned in September is there in the Community Board’s October report. It says the Board was told on 2 September that the intersection upgrade had been pushed back because the wastewater work was taking longer. The start date in that report is late 2027. [3]

The Board received that report at its 5 October meeting. So this is already part of the Council paperwork. [4]

The decision to put in lights was made back on 4 February 2026, when Council voted 15–1 for the signals and associated lanes. [5] By the time construction starts, that decision will be getting on for two years old. That’s only the start of construction, with another stretch of roadworks to follow.

Getting the pipes sorted before building the new intersection makes sense. What I’d like explained is how we get from the current pipe work to another construction stage late next year, and what that means for everyone trying to get around in between.

Illustration: A parent and young child, seen from behind, waiting to cross a wet residential street at night as a car passes on the diversion, with road cones and an orange detour arrow sign
Illustration

A diversion on a map is someone else’s street

There have also been complaints on local Facebook pages about cars speeding and cutting corners along the diversions. Those are residents’ accounts, but they deserve a response.

It’s easy to draw a line around a worksite and send the traffic another way. Living on that “other way” is a different matter. You still have to get out of your driveway, walk past parked cars, cross the road and get the kids where they need to go.

If people are reporting speeding and cars cutting corners, get someone out there to look. Check the speeds. Check the problem corners. Make sure the signs and sightlines work. And if drivers are behaving dangerously, do something about it.

To the drivers: being annoyed about a detour doesn’t give you a free pass to make somebody else’s street unsafe. Slow down. Keep to your side. People live there.

We’ve heard these worries before

Access around here has been an issue for years. In July 2022, Emily Moorhouse’s report on Prestons Park’s exit problems described residents’ frustration with congestion, the wait for the Mairehau Road connection and the limits of Cameo Grove as an alternative. The roads have changed since then, but the frustration in that story sounds familiar.

More recently, Chris Lynch reported on 12 February 2026 that proposed parking charges at Burwood Hospital had raised concerns about more cars spilling into nearby streets. Kelly Barber spoke about complaints over driveway access on Mairehau Road and Cameo Grove, and the safety of children walking to school.

The parking-charge proposal was scrapped later that day. But those concerns about the surrounding streets are a reminder of how little room there is to keep shifting problems onto the neighbours. Parking, through traffic, diversions—it all ends up outside someone’s house.

Illustration: An empty bus shelter on a rainy night, with a laminated notice cable-tied to the bus-stop pole and an orange road cone reflected on the wet footpath
Illustration

Five months is a long time to keep asking for patience

Five months of diversions is a long time to live with. And there’s another round of work ahead.

We’re talking about a route to a hospital, local shops and people’s homes. This is Christchurch. Surely getting around your own neighbourhood safely, without months of uncertainty, isn’t asking too much.

The restrictions have changed as the work has moved along. The whole intersection hasn’t been shut in every direction for five months, and the late-2027 start doesn’t mean it stays closed until then. But from a resident’s point of view, each new stage adds to the same old disruption.

A few extra minutes on one trip might sound trivial. Keep adding them to the school run, work, appointments and shopping, week after week, and it stops feeling trivial. For a small shop, customers finding it awkward to stop can be a much bigger problem.

I understand that buried pipes can throw up surprises. I’m not expecting anyone to wave a wand over a hole in the road. But surely we can expect a clear explanation of why it’s taking this long, what’s being done to finish it, and how the people on the diversions are being looked after.

“Until further notice” wears pretty thin after five months. So does another thank-you for our patience. Give us dates we can plan around, and tell us promptly when they change.

Links and sources

The Council and Metro dates below are the published position on 10 November 2026. The news stories are linked above.

  1. Council: Burwood wastewater upgrade — extra pipe damage and the September–December work timetable.
  2. Metro: Route 7 — westbound Mairehau Road diversion, dated 9 June, still listed on 10 November.
  3. Community Board agenda, 5 October — item 18, section 3.2: intersection construction scheduled to start in late 2027.
  4. Community Board minutes, 5 October — item 18, receiving the October area report.
  5. Council minutes, 4 February — item 10, pages 8–9: approval of traffic signals and associated lanes.